The following updates were made to the Construction Manual located at:

Section 811, 2022 Uniform Price Adjustments for Waterborne Permanent Pavement Markings [ [link removed] ]

In the fall of each year field staff are to process a uniform price adjustment when regular dry or low temperature waterborne paint is substituted for waterborne paint due to seasonal limitations. This price adjustment is to be made in accordance with the Special Provision for Early/Late Season Striping for Permanent Pavement Markings, which is included in all contracts with a combined total of 30,000 ft or more of the pay items: Pavt Mrkg, Waterborne, _inch, (color). Payment is to be processed as noted under section d. Measurement and Payment of the special provision in the contract documents.

The 2022 uniform price adjustment values for regular dry paint and low temperature waterborne paint have been negotiated between Construction Field Services and industry and have been posted in the MDOT Construction Manual in Division 8, Section 811, under the Measurement and Payment heading.

The following table specifies the negotiated price adjustment per lineal foot for changing from Pavt Mrkg, Waterborne, _in (white) to Pavt Mrkg, Regular Dry, _in (white):

*Construction Season*

*4 inch White*

*6 inch White*

*12 inch White*

2022

$0.0190

$0.0300

$0.0600

2021

$0.0240

$0.0360

$0.0720

2020

$0.0110

$0.0160

$0.0330

2019

$0.0100

$0.0150

$0.0300

2018

$0.0096

$0.0145

$0.0289

2017

$0.0066

$0.0098

$0.0197

2016

$0.0086

$0.0130

$0.0259

2015

$0.0082

$0.0122

$0.0245

2014

$0.0090

$0.0135

$0.0270

2013

$0.0095

$0.0143

$0.0286

2012

$0.0092

$0.0138

$0.0276


The following table specifies the negotiated price adjustment per lineal foot for changing from Pavt Mrkg, Waterborne, _in (yellow) to Pavt Mrkg, Regular Dry, _in (yellow):

*Construction Season*

*4 inch Yellow*

*6 inch Yellow*

*12 inch Yellow*

2022

$0.0170

$0.0260

$0.0520

2021

$0.0250

$0.0370

$0.0740

2020

$0.0110

$0.0160

$0.0320

2019

$0.0100

$0.0150

$0.0300

2018

$0.0102

$0.0153

$0.0305

2017

$0.0066

$0.0098

$0.0197

2016

$0.0088

$0.0132

$0.0264

2015

$0.0093

$0.0139

$0.0278

2014

$0.0100

$0.0150

$0.0300

2013

$0.0088

$0.0132

$0.0264

2012

$0.0104

$0.0156

$0.0312


 

 

 

 

 

________________________________________________________________________

 

"The Michigan Department of Transportation: "
"Providing the highest quality integrated transportation services for economic benefit and improved quality of life. "
"www.michigan.gov/mdot [ [link removed] ]  |  www.michigan.gov/drive [ [link removed] ]  |  contact MDOT [ [link removed] ] 
"

 

Manage Subscriptions [ [link removed] ]  |  Subscriber Help [ [link removed] ]  |  Having trouble viewing this email? View it as a Web page [ [link removed] ].
________________________________________________________________________

This email was sent to [email protected] using GovDelivery Communications Cloud on behalf of: Michigan DOT · 425 W. Ottawa St. · Lansing, MI 48909 · 517-373-2090
Screenshot of the email generated on import

Message Analysis