The following updates were made to the Construction Manual located at: Section 811, 2022 Uniform Price Adjustments for Waterborne Permanent Pavement Markings In the fall of each year field staff are to process a uniform price adjustment when regular dry or low temperature waterborne paint is substituted for waterborne paint due to seasonal limitations. This price adjustment is to be made in accordance with the Special Provision for Early/Late Season Striping for Permanent Pavement Markings, which is included in all contracts with a combined total of 30,000 ft or more of the pay items: Pavt Mrkg, Waterborne, _inch, (color). Payment is to be processed as noted under section d. Measurement and Payment of the special provision in the contract documents. The 2022 uniform price adjustment values for regular dry paint and low temperature waterborne paint have been negotiated between Construction Field Services and industry and have been posted in the MDOT Construction Manual in Division 8, Section 811, under the Measurement and Payment heading. The following table specifies the negotiated price adjustment per lineal foot for changing from Pavt Mrkg, Waterborne, _in (white) to Pavt Mrkg, Regular Dry, _in (white): The following table specifies the negotiated price adjustment per lineal foot for changing from Pavt Mrkg, Waterborne, _in (yellow) to Pavt Mrkg, Regular Dry, _in (yellow):
|