*Legislative Campus Modernization Project Weekly Update*





WHAT'S NEW





Newhouse construction




Irv Newhouse Building

Crews continue to remove hazardous materials from the interior of the Newhouse Building and?Wilkeson sandstone and windows from the exterior.

Crews also continue deconstructing the Carlyon House, including the removal and safe disposal of siding that contains lead-based paint. Once this work is complete, crews will begin deconstructing the Ayer House.?

Expected impacts:


* *Traffic/Road Closures
*

On Friday, *March 24 from 7 a.m. - 1 p.m.*, DES will close the eastbound lane on Sid Snyder Avenue (between Columbia Street Southwest and Water Street Southwest) to complete fiber optic work through a manhole. Flaggers will be onsite to direct traffic.


* *Pedestrian
*Two sidewalks bordering the Newhouse Building site are closed, and alternate routes are clearly marked.? Closures are:
* West side of Columbia Street Southwest
* North side of 15th Avenue Southwest

* *Noise
*Minimal noise is expected
* *Hours of operation
*7 a.m. - 4:30 p.m.
* *Parking
*No new impacts






Pritchard




Joel M. Pritchard Building

Design work continues for the Pritchard Rehabilitation Project. The next phase of design will focus on updating costs for the project from initial estimates. ?












*LET'S CELEBRATE*





Sandstone





Crews continue to meticulously remove Wilkeson sandstone from the exterior of the Newhouse Building. All salvageable pieces are being stored for future use.?











GET INVOLVED





Stakeholder




Stakeholder Meeting #17

March 30, 2023 | 3:30 p.m.

During this meeting we will discuss:


* 90-day look ahead
* Pritchard environmental review (SEPA) status
* Newhouse Building Replacement project update
* Pritchard and O'Brien projects update

For more information about the LCM stakeholder meeting and other public meetings, visit the LCM public meetings page [ [link removed] ] on our website.?











contact
*CONTACT US*

*[email protected]*












DID YOU KNOW





LCM Weekly Update cover




The State Library Building - now known as the Joel M. Pritchard Building - is the only structure built solely to house the Washington State Library collection.??Built in 1959, the building was designed by architect Paul Thiry, who also designed the buildings at the 1962 World?s Fair in Seattle. The building was renamed in the late 1970s to honor legislator and civil rights leader Joel M. Pritchard.











LEARN MORE





*Legislative Campus Modernization (LCM) [ [link removed] ]
****Newhouse [ [link removed] ]***
Pritchard [ [link removed] ]
** [ [link removed] ]








Accessibility [ [link removed] ]?| Manage Subscriptions [ [link removed] ]?| Help [ [link removed] ] | Contact Us [ [link removed] ]

If you have trouble viewing this email, view as a web page [ [link removed] ]

DES Twitter feed button [ [link removed] ] ??DES Facebook page button [ [link removed] ] ??Washington State YouTube Channel button [ [link removed] ] ??DES LinkedIn button [ [link removed] ] ??DES Flickr button [ [link removed] ] ??DES Medium button [ [link removed] ] ??DES GovDelivery button [ [link removed] ]

________________________________________________________________________

This email was sent to [email protected] using GovDelivery Communications Cloud on behalf of: Washington State Department of Enterprise Services ? PO Box 41401 ? Olympia, WA ? 98504-1401 GovDelivery logo [ [link removed] ]
Screenshot of the email generated on import

Message Analysis

  • Sender: n/a
  • Political Party: n/a
  • Country: n/a
  • State/Locality: n/a
  • Office: n/a
  • Email Providers:
    • govDelivery