October 2022 ? MDOT Construction Manual Updates

The tables below list all Major and Minor changes to the MDOT Construction Manual in the past several months.??

All changes for the past 12 months can be found in the table of Recent Major Changes and the table of Recent Minor Changes?or can also be found in the Construction Manual on the Main Page.?

Recent Major Changes to the Construction Manual

The table below is a list of Major changes in the last 6 months.

Updated Division Section Summary What Changed
9/19/2022
1 Supplemental
FHWA Risk-Based Project Involvement
Updated content to remove references to FHWA Projects of Division Interest (PoDI) and replaced with FHWA Risk-Based Project Involvement (RBPI). References now link to the FHWA Risk-Based Project Involvement (RBPI) Stewardship & Oversight Plan (S&O Plan) page which contains instructions on how to locate each project's S&O Plan in ProjectWise to determine FHWA involvement. View Here
7/21/2022
1
104.10
Updated Construction Claims Procedure document with July 2022 version. View Here
6/21/2022
8
811
Updated temporary special markings price negotiation costs Compare Here
5/18/2022
Sidebar
AASHTOWare Project Construction & Materials Software Manual (Wiki)
Added the AASHTOWare Project Construction & Materials Software Manual (Wiki) to the left sidebar of the Construction Manual Wiki View Here
5/5/2022
8
811
Updated Durable Pavement Markings and Uniform Price Adjustment, Regular Dry Paint, and Low Temperature Waterborne Paint sections Compare Here
4/19/2022
Sidebar
Documentation Guide 2022
Updated Documentation Guide 2022 View Here
3/16/2022
1
Holiday Traffic Safety Provisions
Updated table to project Holiday Traffic Safety Provisions and Closures dates to 2030 View Here
1/4/2022
1
109.07
Updated contents of entire section 109.07 Final Inspection, Acceptance, and Final Payment Compare Here

?

Recent Minor Changes to the Construction Manual

The table below is a list of Minor changes in the last 6 months.

Updated Division Section Summary What Changed
10/05/2022
8
811
Updated Permanent Pavement Markings payment table to include 2022 prices Compare Here
7/20/2022
307
Aggregate Shoulders and Approaches, Measurement and Payment
Updated moisture content change information under Measurement and Payment Compare Here
7/5/2022
1 supplemental
Dispute Review Board
Updated link to public-facing website for DRB and updated pdf file as of July 2022 Compare Here
7/5/2022
1 supplemental
Certified Engineer List
Updated Certified Engineer List to June 2022 View Here
6/30/2022
1
102.02
Updated lead times for Steel Pipe pile in excess of 14 inches diameter..., Concrete Beams, and added Precast Box Culverts and Ductile Iron Watermain Compare Here
6/7/2022
2
208
Added new Turbidity Curtain section View Here
5/26/2022
1
Process for Documenting Certified Materials in FieldManager
Updated content and added samples Compare Here
4/14/2022
1 Supplemental
Certified Engineer List
Updated Certified Engineer List to April 2022 View Here
4/14/2022
1 Supplemental
Dispute Review Board Process Flowchart
Updated DRB Process Flowchart to 2022 View Here
3/15/2022
1
109.07
Updated and reorganized section to clarifying information Compare Here
2/17/2022
1 Supplemental
e-Construction
Updated alpha/numeric standard naming convention lists as of 2/17/2022 View Here
2/3/2022
1 Supplemental
Certified Engineer List
Updated Certified Engineer List for February 2022 View Here
1/18/2022
1 Supplemental
102.02
Updated Typical Long-Lead Items table Lead Times for Delineator and 3# U-Channel Posts Compare Here
1/5/2022
1
Final Project Review Report
Updated Final Project Review Report User Guide to September 2020 version Compare Here
1/4/2022
1
102.02
Updated/added Typical Long-Lead Items times for Guardrail-Steel Compare Here
1/4/2022
1 Supplemental
Local Agency Program
Added Archeological and Historical Findings resource View Here

?

?