DEP directs NECEC to remove specific materials from the project corridor?
?
*AUGUSTA, October 3, 2022* ??The New England Clean Energy Connect project corridor must be cleared of temporary crane mats and previously cut trees, according to a directive from the Maine Department of Environmental Protection (DEP) to NECEC Transmission LLC.
A condition of the original permit limits the length of time crane mats can remain in place to 18 months.? The remaining crane mats must be removed prior to the onset of winter for NECEC Transmission LLC to remain in compliance with the permit.? The Suspension Order anticipated the need to remove trees which had been cut before construction of the project was suspended.? According to the Order:?"Should vegetation cut prior to the issuance of this Order remain within the transmission line corridor or Project site, this cut vegetation may be removed or chipped and spread consistent with the terms of the License. No new vegetation may be cut so long as the License is suspended. "
Removal of the construction matting and felled trees along the corridor does not constitute restarting of construction and complies with the current Suspension Order's requirements. The removal of these materials before the ground freezes will help those areas to revegetate more quickly.
The tentative schedule for activity on the corridor is as follows:
Segment Number
Approximate Start date
Approximate End date
Approximate Number of Crane Mats to be removed
Approximate miles of tree pick up
Segment 1
10/3/2022
10/11/20/2022
11,800
14.67
Segment 2
10/26/2022
11/29/2022
17,600
0
Segment 3
11/29/2022
12/14/2022
7,175
7.25
The Suspension Order issued by Maine DEP on November 23, 2021, remains in effect.
"For additional information, contact":
David R. Madore, Deputy Commissioner
[email protected] [ link ]
________________________________________________________________________
MEDEP Logo [ [link removed] ]?
*Maine Department of Environmental Protection
*Manage Subscriber Preferences [ [link removed] ] | Unsubscribe [ [link removed] ] | Help [ [link removed] ] | Contact Us
[ [link removed] ]STAY CONNECTED:
??Twitter Logo [ [link removed] ]?GovDelivery Envelope [ [link removed] ]?Bookmark and Share [ [link removed] ]
[ [link removed] ]
________________________________________________________________________
This email was sent to
[email protected] using GovDelivery Communications Cloud on behalf of: Maine Department of Environmental Protection ? 17 State House Station ? Augusta, ME 04333?? 207-287-7688 GovDelivery logo [ [link removed] ]