BREWER - The Maine Department of Transportation will begin work on the next phase of construction for the Brewer Riverwalk on Monday, August 8th. Work will begin at Hardy Street and continue for 900' south along the Penobscot River. Work includes paving a new, ten-foot-wide multiuse path, lighting, WiFi, benches, and trash receptacles. During construction, the shoulder of Route15/South Main Street will be closed. This work will provide enhancements to the existing Riverwalk. Work is anticipated to be completed on 9-20-22. The contractor in Maine Earth out of Hampden. The contract amount is $578,547,00.