Subject AG Nessel on MPSC Not Issuing Decision on DTE’s Data Center Application
Date December 5, 2025 7:45 PM
  Links have been removed from this email. Learn more in the FAQ.
  Links have been removed from this email. Learn more in the FAQ.
Today, the Michigan Public Service Commission (MPSC) held its December 5 meeting without issuing a decision on DTE’s ex parte application





Share or view as webpage [ [link removed] ] | Unsubscribe [ [link removed] ]






Michigan Department of Attorney General Press Release banner [ [link removed] ]




*FOR IMMEDIATE RELEASE:*
December 5, 2025




*Media Contact:*
Danny Wimmer <[email protected]>






AG Nessel on MPSC Not Issuing Decision on DTE’s Data Center Application

*LANSING* – Today, the Michigan Public Service Commission (MPSC) held its December 5 meeting without issuing a decision on DTE’s ex parte application for approval of two special contracts to service a 1.4-gigawatt data center in Saline Township [ [link removed] ]. DTE has repeatedly claimed that the special contracts required approval by December 5. However, in its response to Michigan Attorney General Dana Nessel’s notice of intervention [ [link removed] ], the utility now acknowledges that the publicly-redacted contract allows the deadline to be extended to December 19. Attorney General Nessel issued the following statement in response:  

“DTE has spent weeks insisting that December 5 was a do-or-die deadline for the MPSC to approve its secret deal to service a data center that would use as much power as a million households only to come clean that their hidden contract allows for this so-called deadline to be extended to December 19. This manufactured timeline was all a pressure tactic to rush through a heavily redacted contract that – for some reason – DTE does not want my office or the public to see. 

“Residents have made clear their opposition to these hidden agreements, and their concerns deserve to be fully heard – not brushed aside. This ‘new’ deadline only became public after my office filed a notice to intervene and is precisely why we need a contested case and full public proceedings. We can’t just take DTE’s word that Michigan ratepayers won’t be left footing the bill for this data center.  

“The next MPSC meeting will mark 48 days since DTE filed for an "ex parte "application. That’s nearly 7 weeks of wasted time that could have been used evaluating these contracts, had they been willing to undergo the normal process. The MPSC should not give in to this pressure campaign and should insist on holding full public hearings that are transparent, thorough, and centered on the interests of Michigan residents – as they are expected to do.”

The MPSC’s next regularly scheduled meeting is on December 18. 

###






AG logo [ [link removed] ]





*Media Inquiries* <[email protected]>




*Latest Releases* [ [link removed] ]




*File a Complaint* [ [link removed] ]








Connect with us:

facebook icon [ [link removed] ] x icon [ [link removed] ] youtube icon [ [link removed] ] instagram icon [ [link removed] ] linkedin icon [ [link removed] ] govdelivery icon <[email protected]> threads icon [ [link removed] ]

If you wish to no longer receive emails from us, 
please update your preferences here:
Manage Preferences [ [link removed] ]  |  Delete Profile [ [link removed] ]

Need further assistance?
Contact Us  |  Help [ [link removed] ]

________________________________________________________________________

Get personalized voter information on early voting and other topics at Michigan.gov/Vote [ [link removed] ].

________________________________________________________________________

This email was sent to [email protected] using GovDelivery Communications Cloud on behalf of: Michigan Attorney General · G. Mennen Williams Building, 7th Floor · 525 W. Ottawa St., P.O. Box 30212 · Lansing, MI 48909 · 517-373-1100
body .abe-column-block { min-height: 5px; } table.gd_combo_table img {margin-left:10px; margin-right:10px;} table.gd_combo_table div.govd_image_display img, table.gd_combo_table td.gd_combo_image_cell img {margin-left:0px; margin-right:0px;} table.govd_hr {min-width: 100%;} p, li, h1, h2, h3 { overflow-wrap: normal; word-wrap: normal; word-break: keep-all; -moz-hyphens: none; -ms-hyphens: none; -webkit-hyphens: none; hyphens: none; mso-hyphenate: none; }
Screenshot of the email generated on import

Message Analysis