STATE ENGINEER’S OFFICE PRELIMINARY OPINION OF THE NATRIUM DEMONSTRATION REACTOR WATER SUPPLY AND WATER YIELD ANALYSIS, LINCOLN COUNTY, WYOMING NOVEMBER 2024 The State Engineer’s Office/Surface Water Division completed a comprehensive review of the Water Supply and Yield Analysis Report submitted by Wright Water Engineers, Inc. on behalf of US SFR Owner, LLC for the proposed Natrium Demonstration Reactor Project in Lincoln County, Wyoming.
The Project is currently estimated to use a total of 5,950 acre-feet of water per year, which is equivalent to a continuous diversion of 8.21 cfs. Wright Water Engineers, Inc. conservatively based the Water Supply and Yield Analysis Report on an annual water demand of 6,323 acre-feet of water per year, which is equivalent to continuous diversion of 8.73 cfs. 6,323 acre-feet of water per year is the maximum amount allowed under the agreement between TerraPower, LLC (on behalf of US SFR Owner, LLC) and PacifiCorp, Inc. for use of water from Lake Viva Naughton Reservoir. The projected life of the Project is 60 years including construction, operations, and decommissioning. US SFR Owner, LLC proposes providing the water supply for the Project through the following mechanisms:
The Project will not use groundwater as a source of cooling or potable water, or for other plant needs during the operations or decommissioning phases. The primary water supply for all phases of the Project is surface water.
The Report states that US SFR Owner, LLC is able and willing to accommodate shortages in water supply and adjust operations, as needed.
Based upon the submitted Water Supply and Water Yield Analysis Report, it is the preliminary opinion of the State Engineer’s Office that a sufficient quantity of water for the Project has been adequately demonstrated.
The Natrium Demonstration Reactor Water Supply and Yield Analysis Report (November 2024) and the State Engineer’s Preliminary Opinion (November 2024) in its entirety, are available on the State Engineer’s Office website @ https://seo.wyo.gov/home/news-press-releases
Pursuant to W.S. 35-12-108, the State Engineer’s Office will accept written comments on the Preliminary Opinion through midnight, December 30, 2024. Comments can be submitted to: State Engineer’s Office/Surface Water Division, 122 West 25th Street, Herschler Building, 2W, Cheyenne, WY 82002; or to [email protected]
|