Docket No |
Record No |
Order No |
Order Issue Date |
Company Name |
Caption |
Order Type |
20000-628-EA-22 |
17212 |
29260 |
4/20/2023 |
Rocky Mountain Power |
IN THE MATTER OF THE APPLICATION OF ROCKY MOUNTAIN POWER FOR AUTHORITY TO CONVERT THE PRIMARY FUEL SOURCE FOR JIM BRIDGER POWER PLANT UNITS 1 AND 2 FROM COAL TO NATURAL GAS |
Order Granting Petition for Confidential Treatment and Protective Order |
90000-169-XI-22 |
17151 |
29261 |
4/21/2023 |
General Order Designation |
IN THE MATTER OF THE INVESTIGATION OF GENESIS ALKALI LLC'S REQUEST FOR SPECIAL PERMIT TO INSTALL FLEXSTEEL PIPELINE TECHNOLOGIES, INC., PIPE IN REGULATED NATURAL GAS TRANSMISSION SERVICE PURSUANT TO 49 CFR SECTION 190.341 |
Order |
20003-219-EA-23 |
17241 |
29262 |
4/21/2023 |
Cheyenne Light, Fuel and Power Co. |
IN THE MATTER OF THE APPLICATION OF CHEYENNE LIGHT, FUEL AND POWER COMPANY dba BLACK HILLS ENERGY FOR AUTHORITY TO INCREASE ITS ELECTRIC VOLUNTARY RENEWABLE ENERGY RIDER RATE TO $0.53 PER MONTH PER 100-KWH BLOCK |
Notice and Order |
80032-3-WR-23 |
17283 |
29263 |
4/24/2023 |
Beulah Land Water, LLC |
IN THE MATTER OF THE APPLICATION OF BEULAH LAND WATER, LLC FOR AUTHORITY TO IMPLEMENT A GENERAL RATE INCREASE TO $240.06 PER MONTH WITH INTERIM RATES EFFECTIVE JUNE 1, 2023 |
Suspension Order |
80032-3-WR-23 |
17283 |
29264 |
4/24/2023 |
Beulah Land Water, LLC |
IN THE MATTER OF THE APPLICATION OF BEULAH LAND WATER, LLC FOR AUTHORITY TO IMPLEMENT A GENERAL RATE INCREASE TO $240.06 PER MONTH WITH INTERIM RATES EFFECTIVE JUNE 1, 2023 |
Notice of Application |
30026-68-GM-22 |
17189 |
29265 |
4/24/2023 |
Black Hills Wyoming Gas, LLC d/b/a Black Hills Energy |
IN THE MATTER OF THE APPLICATION OF BLACK HILLS WYOMING GAS, LLC dba BLACK HILLS ENERGY, FOR AUTHORITY TO IMPLEMENT WYOMING INTEGRITY RIDER RATES OF $0.0231 PER THERM FOR RESIDENTIAL GENERAL SERVICE, $0.0139 PER THERM FOR SMALL GENERAL SERVICE, $0.0148 PER THERM FOR MEDIUM GENERAL SERVICE, $0.0092 PER THERM FOR LARGE GENERAL SERVICE, AND $0.0285 PER THERM FOR ON-SYSTEM TRANSPORTATION SERVICE |
Order |
30007-152-GP-23 |
17240 |
29266 |
4/24/2023 |
Frannie Deaver Utilities |
IN THE MATTER OF THE AMENDED APPLICATION OF FRANNIE DEAVER UTILITIES FOR AUTHORITY TO PASS ON A WHOLESALE NATURAL GAS COST DECREASE OF $3.2802 PER MCF |
Notice and Order |
30013-396-GP-23 |
17258 |
29267 |
4/24/2023 |
Montana-Dakota Utilities Co. |
IN THE MATTER OF THE APPLICATION OF MONTANA-DAKOTA UTILITIES CO., FOR AUTHORITY TO PASS ON A NET GAS COST DECREASE OF $1.278 PER DEKATHERM FOR RESIDENTIAL AND FIRM GENERAL CUSTOMERS, AND FOR SMALL AND LARGE INTERRUPTIBLE CUSTOMERS, AND A DECREASE OF $3.666 PER DEKATHERM FOR SEASONAL CUSTOMERS |
Notice and Order |
30026-70-GP-23 |
17229 |
29268 |
4/24/2023 |
Black Hills Wyoming Gas, LLC d/b/a Black Hills Energy |
IN THE MATTER OF THE APPLICATION OF BLACK HILLS WYOMING GAS, LLC d/b/a BLACK HILLS ENERGY FOR AUTHORITY TO PASS ON A GAS COST ADJUSTMENT DECREASE OF $0.0396 PER THERM |
Notice & Order |
80032-3-WR-23 |
17283 |
29269 |
4/25/2023 |
Beulah Land Water, LLC |
IN THE MATTER OF THE APPLICATION OF BEULAH LAND WATER, LLC FOR AUTHORITY TO IMPLEMENT A GENERAL RATE INCREASE TO $240.06 PER MONTH WITH INTERIM RATES EFFECTIVE JUNE 1, 2023 |
Notice of Application Nunc Pro Tunc |
80032-3-WR-23 |
17283 |
29270 |
4/25/2023 |
Beulah Land Water, LLC |
IN THE MATTER OF THE APPLICATION OF BEULAH LAND WATER, LLC FOR AUTHORITY TO IMPLEMENT A GENERAL RATE INCREASE TO $240.06 PER MONTH WITH INTERIM RATES EFFECTIVE JUNE 1, 2023 |
Suspension Order Nunc Pro Tunc |
20003-206-EN-22 |
16998 |
29271 |
4/25/2023 |
Cheyenne Light, Fuel and Power Co. |
IN THE MATTER OF THE APPLICATION OF CHEYENNE LIGHT, FUEL AND POWER COMPANY dba BLACK HILLS ENERGY FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT AND OPERATE ONE NEW 230 kV SUBSTATION, TWO REPLACEMENT 115 kV SUBSTATIONS, THREE 230 kV TRANSMISSION LINES, TWO 115 kV TRANSMISSION LINES AND RELATED FACILITIES IN CONVERSE, LARAMIE, GOSHEN AND PLATTE COUNTIES IN WYOMING AND SCOTTS BLUFF COUNTY IN NEBRASKA |
Memorandum Opinion, Findings and Order Approving Application |
20000-641-EA-23 |
17280 |
29272 |
4/25/2023 |
Rocky Mountain Power |
IN THE MATTER OF THE APPLICATION OF ROCKY MOUNTAIN POWER FOR AUTHORITY TO EXTEND THE 2020 INTER-JURISDICTIONAL COST ALLOCATION AGREEMENT THROUGH DECEMBER 31, 2025 |
Order Authorizing Intervention WIEC |
20003-224-EA-23 |
17282 |
29273 |
4/26/2023 |
Cheyenne Light, Fuel and Power Co. |
IN THE MATTER OF THE APPLICATION OF CHEYENNE LIGHT, FUEL AND POWER COMPANY D/B/A BLACK HILLS ENERGY FOR AUTHORITY TO PASS ON A BLOCKCHAIN INTERRUPTIBLE SERVICE CUSTOMER CREDIT ADJUSTMENT RATE OF $0.00 PER KILOWATT HOUR |
Suspension Order |
20000-588-EN-20 |
15604 |
29274 |
4/26/2023 |
Rocky Mountain Power |
IN THE MATTER OF THE SUPPLEMENTAL APPLICATION OF ROCKY MOUNTAIN POWER FOR SITUS & NON-SITUS CERTIFICATES OF PUBLIC CONVENIENCE AND NECESSITY FOR THE GATEWAY SOUTH TRANSMISSION PROJECT AND THE GATEWAY WEST SEGMENT D.1 TRANSMISSION PROJECT |
Memorandum Opinion, Findings and Order Approving Application |
20000-631-EN-23 |
17236 |
29275 |
4/26/2023 |
Rocky Mountain Power |
IN THE MATTER OF THE NOTIFICATION AND APPLICATION OF ROCKY MOUNTAIN POWER REQUESTING WAIVER OR ISSUANCE OF A NON-SITUS CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY AND WAIVER OR APPROVAL UNDER THE ADVANCED REVIEW PROCESS FOR THE ENERGY GATEWAY SEGMENT H, BOARDMAN-TO-HEMINGWAY 500-KILOVOLT TRANSMISSION LINE |
Notice and Order Canceling Public Hearing |
20003-224-EA-23 |
17282 |
29276 |
4/26/2023 |
Cheyenne Light, Fuel and Power Co. |
IN THE MATTER OF THE APPLICATION OF CHEYENNE LIGHT, FUEL AND POWER COMPANY D/B/A BLACK HILLS ENERGY FOR AUTHORITY TO PASS ON A BLOCKCHAIN INTERRUPTIBLE SERVICE CUSTOMER CREDIT ADJUSTMENT RATE OF $0.00 PER KILOWATT HOUR |
Suspension Order Nunc Pro Tunc |
90072-51-XO-23 |
17226 |
29277 |
4/26/2023 |
General Order Sub Number Designation (WUSF) |
IN THE MATTER OF THE FUNDING REQUIREMENT AND PROPOSED ASSESSMENT FACTOR FOR THE JULY 2023 TO JUNE 2024 FISCAL YEAR OF THE WYOMING UNIVERSAL SERVICE FUND |
Notice of Filing and Procedural Notice and Order Setting Hearing |
10001-24-CT-22 |
17080 |
29278 |
4/27/2023 |
Yampa Valley Electric Association, Inc. |
IN THE MATTER OF THE APPLICATION OF YAMPA VALLEY ELECTRIC ASSOCIATION, INC., FOR AUTHORITY TO REVISE ITS NET METERING LINE LOSS CHARGE |
Letter Order |
20003-217-EM-23 |
17232 |
29279 |
4/27/2023 |
Cheyenne Light, Fuel and Power Co. |
IN THE MATTER OF THE APPLICATION OF CHEYENNE LIGHT, FUEL AND POWER COMPANY d/b/a BLACK HILLS ENERGY FOR AUTHORITY TO DECREASE ITS POWER COST ADJUSTMENT BY $0.03149 PER KILOWATT HOUR |
Order Approving Rates On An Interim Basis |
20003-224-EA-23 |
17282 |
29280 |
4/27/2023 |
Cheyenne Light, Fuel and Power Co. |
IN THE MATTER OF THE APPLICATION OF CHEYENNE LIGHT, FUEL AND POWER COMPANY D/B/A BLACK HILLS ENERGY FOR AUTHORITY TO PASS ON A BLOCKCHAIN INTERRUPTIBLE SERVICE CUSTOMER CREDIT ADJUSTMENT RATE OF $0.00 PER KILOWATT HOUR |
Notice of Application |